Which are the activities of the implementation lifecycle for a permanent P3O?

Which are the activities of the implementation lifecycle for a permanent P3O?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiate, Define, Deliver Capability / Realize Benefits, Close

B.
Identify, Define, Deliver Tranches, Close

C.
Identify, Define, Deliver Blueprint, Close

D.
Identify, Define, Deliver Capability / Realize Benefits, Close