PrepAway - Latest Free Exam Questions & Answers

What is the most likely reason that the team did not meet the Sprint objectives?

A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell
ill and was away for two days right at the beginning of the four week Sprint.
What is the most likely reason that the team did not meet the Sprint objectives?

PrepAway - Latest Free Exam Questions & Answers

A.
The Product Owner is unable to prioritize.

B.
The team is lacking skills.

C.
The team did not plan the Sprint effectively.

D.
The team is over-worked.

2 Comments on “What is the most likely reason that the team did not meet the Sprint objectives?


Leave a Reply