which threshold percent does capacity reach the point where action should be taken to make more free space ava

An EMC Data Domain system has been installed at a customer’s site for several months and has
reached steady state. At which threshold percent does capacity reach the point where action
should be taken to make more free space available?

PrepAway - Latest Free Exam Questions & Answers

A.
75

B.
85

C.
90

D.
95

Explanation: