Certkiller .com would like to create a point-in-time copy of data for development purposes. The customer environment is not performance sensitive. The customer wants to point-in-time copy at 9 AM.
The amount of time required to copy the data from the source to the target is 60 minutes and application downtime is not available.
Which solution would you recommend?

PrepAway - Latest Free Exam Questions & Answers

A.
Use TimeFinder/Clone to create a clone with the Precopy (-precopy) option at or before 8 AM. Activate the clone session before 8 AM

B.
Use TimeFinder/Clone to create a clone with the background copy (-copy) option at or before 8 AM. Activate the clone at 9 AM

C.
Use TimeFinder/Clone to create and activate a clone with the background copy (-copy) option at 8AM

D.
Use TimeFinder/Clone to create a clone using the deferred copy mode (default) prior to 9 AM. Activate the clone with the consistent options at 9 AM