Which report entity must be added to an alert so it flags completed processes that have exceeded a specified t

Which report entity must be added to an alert so it flags completed processes that have exceeded
a specified time threshold?

PrepAway - Latest Free Exam Questions & Answers

A.
process execution

B.
activity duration

C.
performer aggregation

D.
process duration