PrepAway - Latest Free Exam Questions & Answers

which order are the steps performend when creating an EMC NetWorker application-based snapshot?

In which order are the steps performend when creating an EMC NetWorker application-based
snapshot?

PrepAway - Latest Free Exam Questions & Answers

A.
1.Freeze application
2.Flush buffers
3.Take snapshot
4.Thaw application

B.
1.Flush buffers
2.Freeze application
3.Take snapshot
4.Thaw application

C.
1.Freeze application
2.Take snapshot
3.Commit writes
4.Thaw application

D.
1.Commit writes
2.Freeze application
3.Take snapshot
4.Thaw application


Leave a Reply