What should the company consider before making the proposed change?

A company has a RecoverPoint environment with 20 Consistency Groups doing remote
replication. A new building was just acquired for disaster recovery and they want to move to
this new location. The IP addresses and cluster name are going to be changed. What
should the company consider before making the proposed change?

PrepAway - Latest Free Exam Questions & Answers

A.
Changes cannot be made without a full sweep of the replica copies only

B.
The Cluster Modification wizard should be used

C.
Changes cannot be made without a full sweep of the production and replica copies

D.
Additional journal space will be required at the production site