PrepAway - Latest Free Exam Questions & Answers

what order are the steps performed?

When creating an EMC NetWorker application-based snapshot, in what order are the steps
performed?

PrepAway - Latest Free Exam Questions & Answers

A.
1.Freeze application
2.Flush buffers
3.Take snapshot
4.Thaw application

B.
1.Flush buffers
2.Freeze application
3.Take snapshot
4.Thaw application

C.
1.Freeze application
2.Take snapshot
3.Commit writes
4.Thaw application

D.
1.Commit writes
2.Freeze application
3.Take snapshot
4.Thaw application

Explanation: