Three more hours will be needed to power up the servers, bring up the network, and redirect users to site

When planning disaster recovery for two data centers, you find that:
The copy of data at remote site B will lag five minutes behind the production data at site A. It will take two hours
after an outage at site A to decide to shift production to site B. Three more hours will be needed to power up
the servers, bring up the network, and redirect users to site

PrepAway - Latest Free Exam Questions & Answers

A.
What is the Recover Point Objective (RPO) of thisplan?

B.
Five minutes

C.
Five hours

D.
Two hours

E.
Three hours