PrepAway - Latest Free Exam Questions & Answers

How many PDPs need to be connected to an electricity so…

EMC installed a 4 X-Brick cluster in a customer’s Data Center.
How many PDPs need to be connected to an electricity source in order to adequately supply power to all PDUs
of this cluster?

PrepAway - Latest Free Exam Questions & Answers

A.
2

B.
4

C.
6

D.
8


Leave a Reply