Scenario 6 A customer recently implemented an EMC Avamar solution in their primary data
center. The environment consists of several Microsoft applications, including Microsoft
SharePoint, Exchange, and SQL. An EMC Data Domain system was also deployed behind
Avamar as the backup destination for these applications. There are also several file system
clients that have been configured to back up directly to the Avamar server. One Avamar
server and two Data Domain systems have been deployed to support this configuration. The
Avamar server is operating close to full capacity and there is no room for expansion since it
is already fully provisioned with the maximum number of nodes. The Data Domain systems
have plenty of capacity left; each system is currently at 35% of utilization. Refer to Scenario
6. The customer needs to protect a number of new file system clients. How can this be
accomplished?

PrepAway - Latest Free Exam Questions & Answers

A.
Direct their backup data to the Data Domain systems

B.
Change the compression algorithm from lz to gz, freeing up space for the new
clients

C.
Deploy a second Avamar server and configure the new clients on the new server

D.
Increase the garbage collection frequency on the Avamar server