PrepAway - Latest Free Exam Questions & Answers

Explain which statement is correct about the new fault.

After an SP is re-inserted into a CX600 to clear a fault and is powered up, it shows as active in Navisphere manager. Approximately thirty seconds later, Navisphere Manager shows that the SPS is now charging for the same SP. Explain which statement is correct about the new fault.

PrepAway - Latest Free Exam Questions & Answers

A.
This is normal;the SPS is tested after an SP power1 up.

B.
This is a new fault which requires the SPS to be replaced.

C.
This is a new fault which requires the SP to be replaced.

D.
This is normal;the CX 600 tests both batteries daily.