Who must FIRST sign off on the findings in order for the project to move to the next phase?

Document type identification has been completed. Who must FIRST sign off on the findings in
order for the project to move to the next phase?

PrepAway - Latest Free Exam Questions & Answers

A.
Human Resources department

B.
Chief Executive Officer (CEO)

C.
System end-users

D.
Project Manager team