Which of the following would a project manager do NEXT after selecting a vendor for a project? seenagape 11 years ago Which of the following would a project manager do NEXT after selecting a vendor for a project? A.Determine a list of qualified sellers. B.Determine vendor resource availability. C.Hold a bidders conference. D.Negotiate the contract. ← Previous question Next question →