Which of the following is the correct progression of the project life cycle?

Which of the following is the correct progression of the project life cycle?

A.
Planning, initiating, executing, monitoring / controlling, closing

B.
Initiating, planning, executing, monitoring / controlling, closing

C.
Planning, initiating, monitoring / controlling, executing, closing

D.
Initiating, planning, monitoring / controlling, executing, closing