CompTIA Exam Questions

A variance between the planned scheduled work and the actual work completed would initially be highl

A variance between the planned scheduled work and the actual work completed would initially be highlighted in which of the following performance statistics?

A.
CV

B.
SV

C.
CPI

D.
ETC