CompTIA Exam Questions

which of the following impacts?

A project team has determined it will need to source data from a system that was not part of the
project scope. The role of the project manager is to analyze which of the following impacts?

A.
Technical design, schedule, and budget

B.
Business process impacts and resourcing

C.
New software and hardware requirements

D.
Schedule, budget, and quality