CompTIA Exam Questions

Which of the following does the project manager need to update?

The customer now needs the project’s deliverable 3 months earlier than scheduled. The
deliverable’s quality has been reduced so the budget will not be impacted. Which of the
following does the project manager need to update?

A.
Schedule

B.
Project budget

C.
Issues Log

D.
Communications Plan