CompTIA Exam Questions

Which of the following describes a critical path?

Which of the following describes a critical path?

A.
Deliverables that need to be developed for project completion

B.
Timeline that the resources roll on to the project

C.
The earliest schedule that a project can finish all of its activities

D.
The order of activities that takes the longest to complete

Explanation: