CompTIA Exam Questions

When creating a communication plan, the project manager should include the escalation path, format a

When creating a communication plan, the project manager should include the escalation
path, format and frequency of meetings, and:

A.
Budget

B.
Scope

C.
Roles and responsibilities

D.
Risk and issue log