The design activity of a project has the following cost… seenagape 7 years ago The design activity of a project has the following cost attributes:PV = 100,000EV = 20,000AC = 90,000Based on this scenario, calculate the schedule variance. A. -80,000 B. -70,000 C. 10,000 D. 120,000 ← Previous question Next question →