Which of the following documents should the project man…
A project manager is assigned to a project and has not had a handover meeting with the previous
project manager. The new project manager is reviewing the percent of project completion, schedule
progress, and budget constraints. Which of the following documents should the project manager
use to obtain this information?
Which of the following tasks are on the critical path?
There are four parallel, paths on a network diagram. The summer duration d each path is below:
A, C, G: 10 weeks
A, B, F: 8 weeks
D, E, H: 12 weeks
D, B, F: 7 weeks
Which of the following tasks are on the critical path?
Which of the following documents should the project man…
A stakeholder is unaware of a project’s status. Which of the following documents should the project
manager consult to ensure a?stakeholders are notified of project changes? (Select TWO.)
Which of the following actions should the project manag…
During a project assessment, a project manager determines the initial project cost estimates were
incorrect, and there is not enough budget left, including reserves, to complete the project. Which of
the following actions should the project manager take?
Which of the following are critical for the project man…
A project manager provides status reports to a customer on a biweekly basis, but the customer is
very busy and only has a few minutes to review the project. Which of the following are critical for
the project manager to provide?
Which of the following individuals is MOST likely to be…
Which of the following individuals is MOST likely to be a key stakeholder for the product launch
phase of a project?
Which of the following documents should the project man…
A project manager is assigned to a new project that must start immediately. No formal or approved
documents have been authored for the project. The project manager must identify project roles,
justify the business need, and determine project scope boundaries. Which of the following
documents should the project manager create?
which of the fallowing organizational structures would …
In which of the fallowing organizational structures would a project manager have the MOST
authority?
An organization has multiple projects that are appropri…
An organization has multiple projects that are appropriately allocated to projects?
Which of the following conflict resolution techniques h…
Two team members have concluded that documentation is not required due to the size of the
current project. The project manager has encouraged them to align strictly within the process.
Which of the following conflict resolution techniques has the project manager utilized1?