Using the PERT method, which of the following is the correct time estimate for a parts delivery?
An ongoing project requires several parts manufactured at an outside vendor. If the vendor has sufficient quantity and can still ship today, the parts should be received in five days; although in most cases an order of this size requires ten days. Allowing for an upcoming holiday and some potential bad weather the shipment could take up to twenty-one days. Using the PERT method, which of the following is the correct time estimate for a parts delivery?
Which of the following is a representation of the amount of money spent on project work at a point in time?
Which of the following is a representation of the amount of money spent on project work at a point in time?
Which of the following is a representation of the difference between the planned costs of work completed compa
Which of the following is a representation of the difference between the planned costs of work completed compared to the actual cost at a point in time?
Which of the following would the project manager use to document the details of the project closure?
A project is cancelled unexpectedly prior to completion. Which of the following would the project manager use to document the details of the project closure?
Which of the following is the correct progression of the project life cycle?
Which of the following is the correct progression of the project life cycle?
A variance between the planned scheduled work and the actual work completed would initially be highlighted in
A variance between the planned scheduled work and the actual work completed would initially be highlighted in which of the following performance statistics?
In which of the following documents should this have been previously addressed?
During handover stage a customer of a particular project noticed the extended warranty from a particular vendor for a critical application has not been ordered. In which of the following documents should this have been previously addressed?
Which of the following is the method for determining the critical path of a project?
Which of the following is the method for determining the critical path of a project?
Which of the following would be the project managers BEST option?
A project manager has been engaged to deliver a project in South America and does not speak Spanish. More than 50 percent of the project team will be Spanish speaking. Which of the following would be the project managers BEST option?
Which of the following actions should the project manager undertake FIRST?
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?