The NEXT step the project manager needs to take is:

A project team is about to deliver on a two year long project when they are informed of new
Government laws that directly affect the product. The team meets with their stakeholders to
discuss the impact to the project and determine that additional laws need to be taken into
account before go-live. The NEXT step the project manager needs to take is: