Which of the following describes a critical path?
Which of the following describes a critical path?
When creating a communication plan, the project manager should include the escalation path, format and frequen
When creating a communication plan, the project manager should include the escalation
path, format and frequency of meetings, and:
which of the following?
A project starts out as a small three month project. One month into the project, a
stakeholder asks the team for additional functionality, which is estimated to take an
additional three weeks. The project manager implements the functionality while waiting for
approval. This is known as which of the following?
The project manager MUST:
After a project team has almost completed the development on the project’s original
requirements, the users identify functionality that is necessary but was not in the original
requirements. The project manager MUST:
A project risk is defined as a condition or event that:
A project risk is defined as a condition or event that:
The NEXT step the project manager needs to take is:
A project team is about to deliver on a two year long project when they are informed of new
Government laws that directly affect the product. The team meets with their stakeholders to
discuss the impact to the project and determine that additional laws need to be taken into
account before go-live. The NEXT step the project manager needs to take is:
Which of the following is the BEST response?
A project team is meeting monthly for their project risk review. During the brainstorm, one of
the team members mentions that a risk to the project could be a delay with the servers.
Which of the following is the BEST response?
Which of the following conflict resolution techniques results in mutual agreement among conflicting parties?
Which of the following conflict resolution techniques results in mutual agreement among
conflicting parties?
Which of the following conflict resolution techniques emphasizes agreeable points in order to move the project
Which of the following conflict resolution techniques emphasizes agreeable points in order
to move the project forward?
A. Forcing
which of the following is a common cause of conflict with project team members?
In a functional structured organization, which of the following is a common cause of conflict
with project team members?