A company has received the contract to begin developing a new suite of software tools to replace an aging
collaboration solution. The original collaboration solution has been in place for nine years, contains over a
million lines of code, and took over two years to develop originally. The SDLC has been broken up into eightprimary stages, with each stage requiring an in-depth risk analysis before moving on to the next phase. Which
of the following software development methods is MOST applicable?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Spiral model
B.
Incremental model
C.
Waterfall model
D.
Agile model