PrepAway - Latest Free Exam Questions & Answers

Which of the following should the project manager relea…

A project manager working for a large city government is required to plan and build a WAN, which will be
required to host official business and public access. It is also anticipated that the city’s emergency and first
response communication systems will be required to operate across the same network. The project manager
has experience with enterprise IT projects, but feels this project has an increased complexity as a result of the
mixed business / public use and the critical infrastructure it will provide. Which of the following should the
project manager release to the public, academia, and private industry to ensure the city provides due care in
considering all project factors prior to building its new WAN?

PrepAway - Latest Free Exam Questions & Answers

A.
NDA

B.
RFI

C.
RFP

D.
RFQ


Leave a Reply