Which two service components are performed during the implement phase? (Choose two)

Which two service components are performed during the implement phase? (Choose two)

PrepAway - Latest Free Exam Questions & Answers

A.
Staff Training

B.
Design Review

C.
Security Readiness Assessment

D.
Configuration Management

E.
Project Kickoff

F.
Site Readiness Specification

G.
All of the above

Explanation:

Reference: Cisco Lifecycle Services Advanced Security Course – Implement Phase