PrepAway - Latest Free Exam Questions & Answers

Which three pieces of information must be maintained for all stakeholders as part of the change management pro

Which three pieces of information must be maintained for all stakeholders as part of the change
management process? (Choose three.)

PrepAway - Latest Free Exam Questions & Answers

A.
the location of the person who applied the change

B.
the date and time that the change was applied and on which device

C.
the original change request form that indicates why the change is necessary

D.
the size of the change (in bytes)

E.
a description of the actual change itself (configuration, program code, and so on)

F.
the names of the current members of the change advisory board

G.
the industrial protocol that is used