Which statement about the plan is true?

Refer to the exhibit. ROUTE.com is planning to implement load balancing for traffic between
host on the 172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the
implementation plan for this project. Which statement about the plan is true? Select the best
response.

PrepAway - Latest Free Exam Questions & Answers

A.
It is complete as written.

B.
It should include a task to configure multipath to equal a value of 2 on R1 and R4.

C.
It should use a ping instead of a traceroute to validate that load balancing has been
activated.

D.
It should contain a task that documents the changes made to the configurations.

Explanation: