which phase of PPDIOO are the network requirements identified?

In which phase of PPDIOO are the network requirements identified?

PrepAway - Latest Free Exam Questions & Answers

A.
Design

B.
Plan

C.
Prepare

D.
Implement

E.
Operate

F.
Optimize

Explanation:

Plan Phase
The Plan phase identifies the network requirements based on goals, facilities, and user needs.
This phase characterizes sites and assesses the network, performs a gap analysis against bestpractice architectures, and looks at the operational environment. A project plan is developed to
manage the tasks, responsible parties, milestones, and resources to do the design and
implementation. The project plan aligns with the scope, cost, and resource parameters established
with the original business requirements. This project plan is followed (and updated) during all
phases of the cycle.