In the implement phase, project close-out involves which of the following tasks?

In the implement phase, project close-out involves which of the following tasks?

PrepAway - Latest Free Exam Questions & Answers

A.
deliver education based on Staff Planning Development reports

B.
conduct Engagement Profitability Assessment

C.
execute network migration plan

D.
customize ongoing support hand-off kit