You are the project manager and at the completion of the project, you MUST:

You are the project manager and at the completion of the project, you MUST:

A.
Celebrate success with the team.

B.
Evaluate team member performance.

C.
get a sign-off from the customer.

D.
Plan a turnover meeting.