PMI Exam Questions

Which ensures that project objectives are met by monitoring and measuring progress and taking correc

Which ensures that project objectives are met by monitoring and measuring progress and taking corrective action when necessary.

A.
Project controls

B.
Controlling process

C.
Control logs

D.
Project chart

Explanation:
Controlling process ensures that project objectives are met by monitoring and measuring progress and taking corrective action when necessary.