Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her
organizational campus. Tim is the electrical engineer for her company and is the only internal
resource that can complete several of the project activities that deal with the fiber optic cables.
Because Tim is a highly-skilled resource, he is already scheduled on several projects within the
organization and is not available when Beth needs him to complete some of the project activities.
This is an example of which term?
A.
Resource calendar conflict
B.
Matrix network
C.
Organizational process assets
D.
Activity resource requirements
Explanation:
Because the activities in Beth’s project require Tim and his skills. This is an example of an activity
resource requirement. A resource constraint would also have been an acceptable answer.
Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid
project management term.
Answer option C is incorrect. Organizational process assets are things that have been created to
help assist the management of the project.
Answer option A is incorrect. A resource calendar conflict is not a valid project management term.