Which process involves aggregating the estimated costs of the individual schedule activities or work seenagape 11 years ago Which process involves aggregating the estimated costs of the individual schedule activities orwork packages? A.Estimate Costs B.Estimate Activity Resources C.Control Costs D.Determine Budget ← Previous question Next question →