Which process develops options and actions to enhance opportunities and reduce threats to project ob

Which process develops options and actions to enhance opportunities and reduce
threats to project objectives?

A.
Identify Risks

B.
Control Risks

C.
Plan Risk Management

D.
Plan Risk Responses