The process of establishing the policies, procedures, and documentation for planning, developing, ma

The process of establishing the policies, procedures, and documentation for
planning, developing, managing, executing, and controlling the project schedule is
known as:

A.
Plan Schedule Management.

B.
Develop Project Charter.

C.
Develop Schedule.

D.
Plan Scope Management.