You work as a project manager for BlueWell Inc. You are creating the activity list for the project.
The activity list is based on the work packages defined in the project’s WBS. Activities provide a
basis for all of the following information except for which one?
A.
Scope baseline
B.
Executing
C.
Scheduling
D.
Estimates
Explanation:
The project’s scope baseline is not derived or provided by the project’s activity list. The scope
baseline is made of the project’s WBS, WBS Dictionary, and the Project Scope Statement. The
activity list provides for estimating, scheduling, executing, and monitoring and controlling the
project work. The scope baseline is an element of the project management plan. The contents of
the scope baseline include the following: Project scope statement: It includes the product scope
description and the project deliverables, and defines the product user acceptance criteria. WBS: It
defines each deliverable and the decomposition of the deliverables into work packages. WBS
dictionary: It contains the detailed description of work and technical documentation for each WBS
element.
Answer option D is incorrect. Estimates do provide a basis for creating time and cost estimates.Answer option B is incorrect. Activities are executed in the project.
Answer option C is incorrect. Activities are scheduled as part of project planning.