Yolanda is the project manager for her organization. She is creating a performance report for her
sponsor. Typically, the performance report includes all of the following factors except for which
one?

A.
Current status of risk and issues

B.
Quality control activities

C.
Analysis of past performance

D.
Work to be completed next

Explanation:
Quality control activities are not included in the performance report, but are documented in the
quality management plan. A performance report is made by the project team detailing activities,
milestones, problems, accomplishments, and identified issues. Performance reports are used to
report some key information as follows: Current status Scheduled activities Significant
accomplishment for the period Forecasts Issues
Answer option C is incorrect. Analysis of past performance can be included in the performance
report to make the report more elaborate.
Answer option A is incorrect. Current status of risk and issues can be included in the performance
report.
Answer option D is incorrect. Work to be completed next can be included in the performance
report.