You are the project manager of the GHY Project. Management wants you to create a process
improvement plan for your project. Your project will be studied by management and will become a
standard for all future organizational projects based on your project’s performance, approach, and
implementation of project processes. All of the following should be included in your project’s
process improvement plan except for which one?
A.
Process boundaries
B.
Process configuration
C.
Targets for improved performance
D.
Identification of project risks
Explanation:
Identification of the project risks is not part of the process improvement plan. Identify risks is a risk
management process, and risks are recorded in the risk register.
Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets
for improved performance are parts of the process improvement plan.