You work as a project manager for TechSoft Inc. You, the project team, and the key project
stakeholders have completed a round of quantitative risk analysis. You now need to update the
risk register with your findings so that you can communicate the risk results to the project
stakeholders – including management. You will need to update all of the following information
except for which one?

A.
Probabilistic analysis of the project

B.
Probability of achieving cost and time objectives

C.
Risk distributions within the project schedule

D.
Trends in quantitative risk analysis