PMI Exam Questions

which of the following processes?

Rolling wave planning is used as tool and technique in which of the following processes?

A.
Estimate Activity Durations

B.
Define Activities

C.
Develop Schedule

D.
Sequence Activities

Explanation:
Rolling wave planning is the process of planning for a project in waves as the project becomes clearer and unfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project.