Which of the following is controlling changes to the budget. seenagape 8 years ago Which of the following is controlling changes to the budget. A.Control Costs B.Estimate Costs C.Determine Budget D.None Explanation:Control Costs is controlling changes to the budget. ← Previous question Next question →