What type of organizational structure usually experiences the MOST team nervousness at project close

What type of organizational structure usually experiences the MOST team nervousness at project close-out?

A.
Weak matrix

B.
Projectized

C.
Strong matrix

D.
Functional

Explanation:
PROJECTIZED : All organization is by projects. The project manager has total control of projects. Personnel are assigned and report to a project manager