Which of the following includes how requirements activities will be planned, tracked, and reported? seenagape 8 years ago Which of the following includes how requirements activities will be planned,tracked, and reported? A.Configuration management plan B.Scope baseline C.Requirements management plan D.Schedule baseline ← Previous question Next question →