Which of the following are the outputs of Collect Requirements Process?

Which of the following are the outputs of Collect Requirements Process?

A.
Requirements documentation

B.
Requirements management plan

C.
The requirements tractability matrix

D.
All of the above

Explanation:
The outputs of Collect Requirements Process are: requirements documentation (stakeholder’s needs), the requirements management plan (how the requirements will be analyzed and documents), and the requirements traceability matrix (tracking of requirements throughout the project).