On any project, who creates the Lessons Learned document? seenagape 10 years ago On any project, who creates the Lessons Learned document? A.Customers B.Project team C.Project sponsor D.Stakeholders Explanation:The project team contributes to the Lessons Learned document. ← Previous question Next question →