PMI Exam Questions

Which of the following are NOT outputs of the Activity Duration Estimation process?

Which of the following are NOT outputs of the Activity Duration Estimation process?

A.
Activity duration estimates

B.
Schedule baseline

C.
None of the choices are correct

D.
Updates to activity attribute