PMI Exam Questions

Which of the following are included in the risk register?

You are the project manager for TTP project. You are in the Identify Risks process. You have to
create the risk register. Which of the following are included in the risk register? Each correct
answer represents a complete solution. Choose two.

A.
List of mitigation techniques

B.
List of key stakeholders

C.
List of identified risks

D.
List of potential responses