Which of the following activities is not part of Plan Risk Management?

Which of the following activities is not part of Plan Risk Management?

A.
Updating Risk register

B.
Determining risk roles and responsabilities

C.
Identifying risk categories

D.
Developing a risk management plan

Explanation:
Updating Risk register first happens in Identify Risk Phase. Determining risk roles and responsabilities, Identifying risk categories, and Developing a risk management plan are part of Plan Risk Management